FAT, SAT, and industrial commissioning: what they are, how they differ, and why they reduce risks before startup
What are FAT, SAT, and industrial commissioning?
Before commissioning an industrial system, there are several stages to verify that equipment and solutions operate as expected. Among the most common are FAT testing, SAT testing, and commissioning.
Although all three concepts are related to validating a solution, they do not mean the same thing. In simple terms:
- FAT: verifies the system before it is taken to the site.
- SAT: checks its operation once installed in the field.
- Commissioning: validates that the entire system is ready to enter operation correctly.
These stages help identify errors, incompatibilities, or pending configurations before they become problems during operation.
In industrial projects involving telecommunications, automation, SCADA, PLC, CCTV, security systems, or other technologies, this validation is especially important.
What is a FAT test?
FAT stands for Factory Acceptance Test. Its purpose is to verify equipment or systems before shipping them to the installation site. Depending on the project, a FAT can evaluate aspects such as:
- Supplied components and equipment.
- Configurations.
- Communications.
- Control logic.
- Interfaces.
- Signals.
- Alarms.
- Documentation.
- General system operation.
The idea is to detect as many problems as possible before the equipment reaches the field. This has a major advantage. Correcting a configuration, replacing a component, or resolving an incompatibility in a controlled environment is usually much simpler than discovering the same problem when the project is already installed and operational constraints exist.
Does a FAT guarantee that everything will work in the field? No.
FAT allows for system validation under pre-installation conditions, but it does not necessarily reproduce all the variables that will exist on-site. Factors related to the following may still arise:
- Cabling.
- Power supply.
- Environmental conditions.
- Existing networks.
- Integration with other systems.
- Field instrumentation.
- Actual distances.
- Available infrastructure.
That is why there is a second validation stage: the SAT.
What is a SAT test?
SAT stands for Site Acceptance Test. It is conducted once the equipment has been installed in its final location. Here, the focus shifts. During the FAT, you verify:
Does the system work?
The SAT aims to verify:
Does the system work correctly within the actual installation?
This allows for checking conditions that can only be validated once the solution is connected to the final infrastructure. For example, the following can be checked:
- Signals from the field.
- Communication between equipment.
- Integration with existing systems.
- Addressing.
- Networks.
- Alarms.
- Inputs and outputs.
- Interfaces.
- Device operation.
- Installation conditions.
SAT helps identify differences between the controlled environment of the FAT and actual operating conditions.
FAT vs. SAT: what is the difference?
The main difference is where and when the validation takes place.
FAT
Performed before final installation. Its purpose is to validate that the supplied system or equipment meets the defined requirements before it is shipped to the field.
SAT
Performed after installation. It seeks to validate that the system functions correctly in its real-world environment, connected to the equipment, networks, and infrastructure with which it will operate.
Both tests complement each other. A successful FAT does not eliminate the need for a SAT. And going straight to a SAT without sufficient prior validation can increase the number of issues that must be resolved on-site.
What is industrial commissioning?
Commissioning is a broader stage. Its goal is to verify that the installed systems are correctly configured, integrated, and ready for operation.
It is not just about checking that a piece of equipment turns on; you must verify that the different parts of the solution work together. In an automation project, for example, this could involve validating communication between instrumentation, PLC, and SCADA.
In telecommunications, it may require verifying links, availability, coverage, and service functionality; in video surveillance, it may involve checking cameras, recording, storage, analytics, and display. The scope depends on each project.
Why is commissioning important?
Because a project can be physically installed and still not be ready to operate. A cable might be connected, a server powered on, a PLC configured, and a camera streaming video, but you still need to verify how everything works together. Commissioning closes that gap between “it’s installed” and “it’s ready to operate.”
What problems can FAT, SAT, and commissioning detect?
These stages can reveal issues such as:
- Incorrect configurations.
- Equipment that does not meet expectations.
- Communication failures.
- Incorrectly assigned signals.
- Discrepancies between engineering and the field.
- Incompatibilities.
- Poorly configured alarms.
- Integration issues.
- Installation errors.
- Missing components.
- Pending documentation.
Detecting these situations before startup can prevent operations from becoming the place where problems that could have been resolved beforehand are discovered.
Why do these tests reduce project risk?
Because they allow for progress in stages. Instead of installing everything and finding out at the end if it works, different validation points are created.
First: validate the solution before shipping it.
Next: verify it in the field.
Finally: ensure the entire system is fully ready to operate.
This sequence helps reduce uncertainty. It also makes it easier to document findings, make corrections, and obtain acceptance before moving on to the next phase.
FAT and SAT in real-world projects
These stages are a recurring part of Apollocom's industrial projects. For example, in telecommunications, automation, terminal, plant, and other infrastructure projects, FAT, installation, configuration, SAT, commissioning, and startup tests are included.
In our recent security, monitoring, and communications project for an ethane terminal, jetty, and pipeline, the scope included exactly that: factory testing, installation, configuration, site testing, commissioning, and startup.
This shows that validation is not an isolated activity: it is part of the complete implementation cycle.
What is the standard order?
Although every project can have its own unique requirements, a typical sequence looks like this:
Engineering → supply → FAT → installation → configuration → SAT → commissioning → start-up.
Not all projects use the exact same stages or scope. That is why the criteria for determining when a solution is considered accepted and ready to move forward must be defined during the engineering phase.
What happens after commissioning?
Once the solution is validated, start-up can begin. Depending on the project, activities such as the following may also follow:
- Training.
- Documentation handover.
- Monitoring.
- Support.
- Maintenance.
- Help desk.
- Warranty management.
This is important because the system's lifecycle does not end upon delivery; a new phase begins: keeping it running.
Frequently asked questions about FAT, SAT, and commissioning
What does FAT stand for?
Factory Acceptance Test. It is an acceptance test performed before the system is installed at its final location.
What does SAT stand for?
Site Acceptance Test. It is a validation performed on-site once the system has been installed.
What is the difference between FAT and SAT?
FAT verifies the system before it is taken to the field. SAT validates its performance within the actual infrastructure where it will operate.
What is commissioning?
It is the process of verifying that equipment, systems, and integrations are correctly configured and ready to enter operation.
Is commissioning the same as start-up?
They are related, but not exactly the same. Commissioning validates that the system is ready; start-up represents its transition into operation.
Do all industrial projects require FAT and SAT?
It depends on the scope, criticality, and characteristics of the project. Criteria must be defined during the engineering and contractual documentation phases.
Conclusion
In industrial projects, discovering a problem before startup is almost always preferable to discovering it once operations are already dependent on the system.
FAT, SAT, and commissioning create different opportunities to verify that the solution is progressing correctly. FAT helps verify before installation, SAT validates under real-world conditions, and commissioning confirms that everything is ready to function as a complete system.
More than just technical formalities, these stages help reduce uncertainty and increase confidence before a solution goes live.